Insmed, a biopharmaceutical company, faced a late-stage shift in strategy when a Phase II feasibility study in a new indication became the program-leading first trial. That change required establishing data collection standards on short notice and managing numerous last-minute protocol and CRF design changes that threatened existing timelines.
Insmed partnered with Veeva Vault CDMS and a dedicated Veeva team to run an agile, in-person CRF design process with real-time updates, a shared sandbox, and a joint change log. The team built 30 eCRFs (22 directly from the protocol), completed rules and edit checks within a week, integrated with Suvoda IVRS, and finished UAT in seven days (32 issues found and resolved), enabling Insmed to meet its deadline and successfully go live.