Case Study: Statoil saves 1.5 drilling days with SLB's integrated drilling system

A SLB Case Study

Preview of the Statoil Case Study

Dual-Reamer Rathole-Elimination RSS BHA Saves 1.5 Drilling Days USD 425,000 for Statoil

SLB worked with Statoil in the North Sea Statfjord field, where the operator needed to sidetrack, drill, and enlarge a challenging 12¼-in × 13½-in section while keeping directional control, avoiding hole collapse, and maintaining a smooth dogleg below 45° in a formation prone to creep and collision risk. The operation also needed to minimize openhole exposure and reduce the time required to run and cement an 11¾-in liner to target depth.

SLB designed an integrated BHA using the Rhino RHE dual-reamer rathole-elimination system, PowerDrive Xceed RSS, C-Link IMAG communication, TeleScope telemetry, and arcVISION services. The system drilled and underreamed the 601-m interval and 49-m rathole in one run, eliminated a dedicated rathole cleanout run, and allowed the liner to be run and cemented successfully, saving Statoil 1.5 drilling days and about USD 425,000.


Open case study document...

SLB

768 Case Studies