Aggreko
229 Case Studies
A Aggreko Case Study
A large producer of building systems and construction products faced major financial risks from an unreliable power grid in South Africa. A utility transformer failure meant that power outages would cause their furnace to cool, leading to the loss of production material costing an estimated 1 million ZAR per day. To prevent these losses, the customer engaged Aggreko to provide a guaranteed standby power solution.
Aggreko installed four 1250 kVA generators at 22kV to ensure the furnace remained operational during grid outages. The solution was kept in place for seven months until the utility resolved the grid issue. By preventing any downtime during this period, Aggreko helped the customer avoid potential losses of 1 million ZAR per day, safeguarding their production and finances.
Large Building Systems and Construction Products Producer