Aggreko
229 Case Studies
A Aggreko Case Study
An international oil company faced a significant challenge in transporting a massive new offshore platform from South Korea to the North Sea. During the four-month tow, the internal heat and humidity threatened to damage critical electrical systems. They engaged Aggreko to provide a reliable cooling and dehumidification solution to protect the asset throughout the voyage.
Aggreko deployed three AC100 air conditioning units, a generator, and a specialized team to manage temperatures and maintain humidity below 60%. This comprehensive approach ensured the platform arrived in perfect condition. The project was completed on schedule, and Aggreko's global logistics and expertise helped cut the subsequent commissioning phase by 8-12 weeks, saving significant time and cost for the customer.
International Oil Company