A leading cement producer in Senegal needed to improve the alignment of a critical drum mill train to reduce excessive vibration and mechanical wear. They partnered with ACOEM, which used its AT-400 system to address the challenge of achieving precise alignment over a long machine train where traditional methods were insufficient.
ACOEM implemented a precise laser alignment solution across the 5-meter train, which included the drum mill, gearbox, and motor. This resulted in a significant reduction in vibration and mechanical wear, enhancing the equipment's operational efficiency and reliability. The impact for the customer included an extended service life for key components and improved overall plant productivity, strengthening their trust in ACOEM solutions.