Wood
30 Case Studies
A Wood Case Study
Chevron required an economically viable facility design for its Anchor deepwater ultra-high pressure development in the Gulf of Mexico. As a long-term strategic contractor, Wood was challenged to deliver a fully integrated engineering design and leverage new methods for future similar projects.
Wood executed the project using a fully digital, cloud-based, and data-driven engineering delivery model. This approach reduced engineering manhours by 20% and enabled a seamless transition to remote work during the pandemic. The solution designed by Wood helped pave the way for future global ultra-high pressure developments.