Ward Leonard, a manufacturer of control systems, electric motors and relays for defense and industrial customers, needed to increase efficiency, simplify its supply chain, improve quality, speed responsiveness, and shorten delivery times. WM Synergy implemented Infor VISUAL (VISUAL ERP) to provide a single, accessible information system across locations and consolidate processes.
Using VISUAL ERP deployed by WM Synergy, Ward Leonard raised shop efficiency from 82% to over 95%, improved on-time delivery from 68% to 92%, and cut major product lead times from 26 to 12 weeks; shop dispatch execution increased from 33% to 77%. The WM Synergy solution also improved inventory accuracy, internal communication, scheduling and supplier collaboration, reducing costs and processing time while enabling better capacity and exception management.