WM Synergy
71 Case Studies
A WM Synergy Case Study
Streamline Industries, a Jeanerette, Louisiana-based machining and custom-manufacturing company, was missing delivery dates and struggling with priorities because its scheduling relied on spreadsheets and JobBOSS’s limited tools. To gain the flexibility and real-time prioritization they needed, Streamline turned to WM Synergy and its Protected Flow Manufacturing (PFM) approach.
WM Synergy implemented PFM (including the Predictor™ simulation tool) to provide real-time priorities, rapid what-if scheduling, and better visibility for managers. As a result, Streamline’s on-time deliveries jumped from a monthly low under 70% before PFM to 100% for the last two months and exceeded 95% in four of the past five months, while also improving quoting accuracy and operational confidence.
Derek Segura
Project Manager