Case Study: Geotronics maps railway on time with WingtraOne by Wingtra

A Wingtra Case Study

Preview of the Geotronics Case Study

Mapping railway and meeting deadlines despite dense forest and rough weather

Geotronics, working with surveyors from Usługi Geodezyjne Leszek Kaczkowski, needed to map a 115 km railway section between Szczytno and Ełk in just one week. The job was made harder by strong winds, rain, and 40 km of dense forest with limited take-off and landing space. WingtraOne was the drone platform used for the project.

Using WingtraOne, Geotronics completed the full railway survey in a week with just three people, instead of the multiple teams and month-long effort classical methods would have required. Wingtra’s precise take-off and landing capabilities, along with the high-end PPK module, enabled efficient operations in rough weather and delivered data at 2 cm accuracy, on time and to spec.


View this case study…