Case Study: Termelétrica Viana S/A achieves 175 MW flexible power generation with Wärtsilä Energy

A Wärtsilä Energy Case Study

Preview of the Termelétrica Viana S/A Case Study

Termelétrica Viana deploys 175 MW power plant with Wärtsilä Energy

Termelétrica Viana S/A faced the challenge of meeting increasing future power demand in a remote location with challenging infrastructure. They partnered with Wärtsilä Energy for a total power plant solution to address this.

Wärtsilä Energy implemented a turnkey solution comprising twenty Wärtsilä 20V32 engines, which provided 175 MW of output and was capable of operating in a hot stand-by mode with short notice switchover to baseload. The results included low fuel consumption over a wide load range and a low overall lifecycle cost, supported by Wärtsilä's full operations and maintenance services.


View this case study…

Wärtsilä Energy

63 Case Studies