Vision Solutions
183 Case Studies
A Vision Solutions Case Study
Terminal de Contenedores de Yucatán (TCY), part of the TCB Maritime Group, operates a major port in Progreso, Yucatán, handling container movements that affect millions of customers. Because TCY must track every container and provide 24/7 online information from a hurricane-prone location, past server failures (including a week-long outage) posed serious risks to operations, customer service and regulatory compliance.
TCY deployed Vision Solutions’ iTera HA to replicate continuously between IBM iSeries production and backup servers, with hardened, geographically separated data centers. The quick three-week rollout proved its value during Hurricane Dean: systems resumed immediately with no data loss. The implementation now guarantees continuous availability, faster recovery, uninterrupted backups and maintenance, improved security and support for ISO 9001:2000 quality requirements.