Virtustream
13 Case Studies
A Virtustream Case Study
Lawrence Graham (LG), a 500‑person law firm with 85 partners handling highly document‑intensive work, faced a stalled virtualization project: partial virtualisation caused frequent outages, slow provisioning, and no concrete disaster‑recovery policy, leaving business confidence and application availability at risk. After relocating premises, LG engaged Virtustream to re‑assess and reinvigorate the virtual estate.
Virtustream implemented a Virtualization Environmental Design Initiative (VEDI), recommended a full architecture (HP 8000 EVA with 12 blade and 13 VMware ESX servers in production, Virtual Centre v2.5; HP 4000 EVA with 6 blade and 6 ESX servers for DR) and executed consolidation and DR clustering. The result: 80% virtualized, lower hardware and utility costs, guaranteed disaster recovery, stabilized Exchange/Filesite/SharePoint environments, easier management, demonstrable CO2 and cost savings, and a roadmap toward VDI and virtualized SANs.