Case Study: BAM Contractors achieves faster room-by-room progress monitoring and reduced paperwork with Viewpoint's Field View

A Viewpoint Case Study

Preview of the BAM Contractors Case Study

BAM Contractors - Customer Case Study

BAM Construct was contracted to deliver the 30,000 m² Mittal Children’s Medical Centre expansion at Great Ormond Street Hospital, a complex, high-spec NHS project divided into 700 individual areas with intensive pre-closure inspections and tight milestone deadlines. The challenge was to monitor progress quickly and accurately across numerous rooms and trades without burdensome paperwork slowing managers down.

BAM deployed Viewpoint’s Field View on PDAs with weekly dropdown checklists and a traffic‑light status system, enabling room-by-room inspections, automated syncing to PCs and visual bar‑chart reporting. The solution cut on-site paperwork, freed managers to focus on critical tasks, made it easy to spot and investigate process problems, and is now being extended from progress monitoring into snagging and other site activities.


Open case study document...

BAM Contractors

Richard Pateman

Construction Manager


Viewpoint

120 Case Studies