Victaulic
66 Case Studies
A Victaulic Case Study
A Permian Basin production facility owner faced the challenge of constructing a new production facility with a need to mitigate risk, maximize onsite productivity, and maintain a compressed construction schedule. They partnered with the vendor Victaulic for vertically integrated fabrication solutions for their piping systems.
Victaulic's in-house modeling team designed the piping systems, and the pipe was prefabricated offsite and delivered in sequenced shipments. Victaulic field engineers provided on-site training and support. This solution led to seamless installation, with 95% of the project installed in just over two weeks. By partnering with Victaulic, the facility was brought online on time and on budget.
Permian Basin Production Facility Owner