The customer, a principal owner of a Permian Basin production facility, required a new production header assembly. They turned to Victaulic for its mechanical joining solutions, seeking the benefits of a lightweight design and ease of installation to meet a compressed construction schedule.

Victaulic provided a modularized system fabricated in-house, which included custom skid drawings and couplings. This solution drastically reduced installation time; the header assembly was completed on-site in just four hours, a task that would have otherwise taken two to three days. Based on this success and the measurable time savings, the owner plans to use Victaulic on future projects.


View this case study…