An owner in North Dakota faced the challenge of bringing a new oil and gas production facility online as quickly as possible while mitigating the risk of schedule delays. To meet this compressed construction schedule, the owner partnered with vendor Victaulic for its value engineered solutions, which included fabrication and virtual design & construction services.
Victaulic's solution involved its in-house modeling team designing the facility and fabricating the piping system off-site. The pre-fabricated sections were shipped by zone to match the site's unique build schedule. This approach allowed for the entire piping system to be installed onsite in just three days. As a result, Victaulic helped ensure the facility was brought online both on time and on budget, which led the owner to partner with them again for a subsequent site expansion.
Owner in North Dakota