The Brisbane City Council required a fast and reliable pipe joining method for the Legacy Way Tunnel infrastructure project to meet a reduced construction schedule. The contractor, MECA, selected Victaulic Installation-Ready rigid and QuickVic flexible couplings for the installation of the fire protection systems.
Victaulic's solution, which featured couplings with no loose parts, simplified assembly and improved on-site safety. By utilizing these products for prefabrication, the contractor estimates they saved six hours of assembly time per manifold array, significantly accelerating the project timeline.