Case Study: Ecorec Slovensko achieves successful remote commissioning and lower costs with Vecoplan waste processing solutions

A Vecoplan Case Study

Preview of the Ecorec Slovensko Case Study

Successful Waste Processing With Successful Remote Commissioning

The customer, Ecorec Slovensko, required solutions to process waste into alternative fuels but faced a challenge when Vecoplan technicians were unable to travel for on-site installation and commissioning due to COVID-19 restrictions. Vecoplan provided a solution with the delivery of VEZ 2500 series pre-shredders to the customer's location in Slovakia.

Vecoplan implemented a remote commissioning process, guiding local electricians via video conferencing and cameras to successfully install and test the equipment. This approach eliminated travel costs for the vendor and provided the customer's team with valuable hands-on experience for future troubleshooting.