The pump manufacturer SEEPEX faced delivery reliability issues due to unrealistic scheduling and a lack of transparency in its complex production planning. Its existing SAP and Excel-based tools were ineffective at managing capacities. To address this, SEEPEX partnered with the vendor valantic.
valantic implemented its advanced planning & scheduling software, wayRTS, to centralize and optimize planning at SEEPEX's headquarters in Bottrop. This solution provided realistic scheduling, improved visualization, and simulation capabilities. The results included nearly doubled delivery reliability, significantly reduced throughput and delivery times, and enhanced planning transparency, leading to successful rollouts at other global plants.