Trimble
839 Case Studies
A Trimble Case Study
SUMMIT Constructors, a Nashville‑based grading and utility contractor, was hired to build a one‑million‑square‑foot building pad for a major sports apparel company under a strict four‑month schedule and exposure to roughly $13,000 per day in liquidated damages. The 67‑acre site required moving 700,000 cubic yards of material through tough limestone/shot rock, and SUMMIT needed a more reliable machine‑control solution after disappointing results with a previous vendor.
Working with SITECH and Trimble 3D machine control (SPS855/SPS985/GCS900/SCS900, Business Center‑HCE and related hardware), SUMMIT equipped dozers and survey crews with GNSS base stations, rover antennas and data‑collection workflows. The result: field staking cut by 50%, finish‑grading time reduced by about 30%, field calculations down 75%, shot‑rock excavation achieved a 38‑foot fill with no imported rock (saving ~$130,000), grading accuracy to one‑tenth of an inch, on‑time completion, and new contracts won thanks to faster, more accurate delivery.
David Haggard
Survey Manager