Case Study: Power Group achieves on-time Cape Town runway rehabilitation and doubles nightly milling output with Trimble 3D milling (PCS900)

A Trimble Case Study

Preview of the Power Group Case Study

Power Group - Customer Case Study

Power Group, a South African construction and engineering firm, was awarded the 11-month rehabilitation of Cape Town International Airport’s main runway, including milling 4,500 m² of asphalt and placing 35,000 t of wearing course. Work could only be done nightly (00:30–05:15) with tight level tolerances (±8 mm) and an IRI rideability target of 1.26; conventional survey set-ups consumed valuable time and limited milling production to ~120 t/night (vs. the 200 t/night needed), putting the contract, schedule and reputation at risk.

The team implemented Trimble 3D milling control (PCS900/GCS900) and ran a rapid laser scan to optimise the design and identify low spots before milling. After installation on their Wirtgen machine the system reached 220 t/night by the third night, met the handover date, and exceeded quality targets—the final averaged IRI was 1.16 (earning a bonus). The project established best practices (pre-scans, accurate benchmarks, dual UTS, drum and hydraulic maintenance) and made 3D control standard on subsequent runway work.


Open case study document...

Power Group

Gary Hirst

Technical Executive


Trimble

839 Case Studies