Kitchell Corporation, an employee‑owned general contractor with over US$350M in annual revenue, faced the challenge of managing a US$100M fast‑track hospital project that demanded stronger collaboration, tighter owner oversight and better risk control. The company needed a standardized, long‑term project management platform to improve accountability and speed up information distribution among contractors, designers and owners.
Kitchell extended its decade‑long use of Prolog Manager by implementing Prolog Converge (configured and deployed with Dimension 5 Solutions), creating a shared database, centralized document repository, automated notifications and role‑based screens. The integrated solution accelerated RFI and submittal processing, solved version‑control and file‑size issues, increased subcontractor accountability, improved owner access and oversight, and reduced project risk.