Trane Commercial
350 Case Studies
A Trane Commercial Case Study
The University of Memphis faced a significant challenge when four aging centrifugal chillers, critical for cooling its research labs and campus buildings, neared the end of their operational life. The high cost of full replacement and a 48-week lead time posed an unacceptable financial risk and threatened to disrupt vital research. The university partnered with Trane Commercial to utilize its CenTraVac R'newal overhaul service as a solution.
Trane's overhaul program extended the chillers' life expectancy by ten years and reduced the university's capital investment by 80-85% compared to full replacement. The process was staggered so each unit was only offline for three weeks, avoiding a year of downtime. The solution also included an upgraded building automation system from Trane, which significantly improved climate control stability and energy efficiency across the campus.