The Massachusetts Bay Transportation Authority engaged McMahon Associates to audit selected bus stops for ADA and MBTA accessibility requirements, identify deficiencies, and develop provisional cost estimates and design improvements. Field technicians used TRAISR’s Asset Central module on tablets to capture linked data, sketches and photos in the field for immediate upload.
Using TRAISR, field data was available in real time and centrally downloadable, enabling generation of audit reports and provisional cost estimates for each stop; McMahon is now developing preliminary designs for accessibility improvements at 50 priority bus stops in nine municipalities. TRAISR-supported audits covered landing areas, paths of travel, curb ramps and amenities, giving MBTA actionable, measurable information to prioritize and budget upgrades.