TraceAir
29 Case Studies
A TraceAir Case Study
The New Home Company faced significant challenges in achieving precise site balance and grading efficiency for their large-scale Russell Ranch development project. They needed a way to move 2 million cubic yards of earth accurately to avoid costly schedule delays and budget overruns caused by outdated or inaccurate topographic surveys. To overcome this, they utilized the site intelligence platform from TraceAir.
By implementing TraceAir's drone-based technology, the project team received highly accurate, 3D topographic maps in less than 24 hours at a fraction of the cost of traditional methods. This real-time data allowed the grading contractor to precisely track material swell, optimize haul routes, and correct balance issues early. As a result, TraceAir helped the project complete ahead of schedule in December 2018, avoiding an estimated $500,000 in potential costs and finishing within 5,000 cubic yards of perfect balance for the massive earthwork operation.