Pardee Homes faced a significant challenge with its 500-acre Skyline Ranch grading project, which required moving 27 million cubic yards of earth in just 16 months. The hilly site and the need to build out of sequence due to pending approvals risked serious dirt imbalance, a problem most contractors believed was beyond their capacity. Pardee Homes partnered with grading contractor ICC, who proposed using TraceAir's drone-powered Balance Solution to address these challenges.
By implementing TraceAir's platform, the project team received near real-time 3D maps and precise cut/fill data twice a week. This allowed them to identify a potential 600,000 cubic yard dirt excess early and revise the grading design accordingly. Using TraceAir resulted in the project finishing two months ahead of schedule with only 20,000 cubic yards of long haul, achieving an unprecedented 99.9% accuracy in site balance. The technology also cut grading meeting times in half and provided the team with the tools to eliminate rework and reduce costs.