Yates Construction used Touchplan to manage the complexity of converting the former Gibson Guitar site in Nashville into 380 high-end residential units, retail spaces, amenity floors, and a multi-level parking garage. With so many trades and project roles involved, the team needed a better way to coordinate weekly planning and keep everyone aligned in real time.
Using Touchplan’s collaborative planning platform, Yates Construction had trade partners enter three weeks of lookahead work ahead of Monday meetings, then updated activities live as the week progressed. By modeling one floor and repeating the workflow across the tower, the team improved consistency and accountability and ultimately topped out the project 35 days ahead of schedule, demonstrating a measurable gain from Touchplan’s planning process.
Tim Tyler
Senior Project Manager