The Toll Group was engaged by the Olympic Dam Mine to transport two massive heat exchangers from a manufacturing site in New South Wales to their mine site in South Australia. The challenge involved moving cargo weighing over 250 tonnes across 2250km of challenging terrain, including mountain ranges and populated areas, while navigating issues like rail bridges and overhead wires.
Toll Group's solution utilized a powerful 115-meter long convoy of specialized heavy haulage equipment, including multiple prime movers and widened platform trailers. Their comprehensive planning involved coordinating with engineers and local authorities to safely lift obstacles and secure route authorizations. As a result, Toll Group successfully delivered both heat exchangers on the 14-day journey without any incidents.