SWTCH
23 Case Studies
A SWTCH Case Study
The Shannon Wall Centre, a property with over 300 parking stalls, faced the challenge of meeting the rising demand for electric vehicle charging from tenants without incurring over a million dollars in costly electrical infrastructure upgrades. They sought a smarter solution and partnered with EV charging vendor SWTCH to implement their SWTCH Control load management system.
By using SWTCH Control's advanced algorithms to dynamically manage power allocation, the installation was able to support eight chargers per electrical circuit instead of just one. This solution from SWTCH allowed them to electrify 220 parking spots and saved the property over one million dollars that would have been required for a traditional installation. The project was a success, with high resident adoption and a future-ready infrastructure that allows for easy expansion.