Case Study: Bramley, UK achieves record-fast 331 MWh BESS commissioning with Sungrow PowerTitan 2.0

A Sungrow Case Study

Preview of the Bramley, UK Case Study

Bramley, UK reaches commercial operation 72% faster with Sungrow

The customer, Bramley in the UK, faced the challenge of deploying a large-scale 100 MW/331 MWh battery energy storage system (BESS) under an extremely tight schedule. To meet this challenge, they partnered with vendor Sungrow and selected their PowerTitan 2.0 integrated energy storage system to ensure a rapid and efficient deployment.

Sungrow implemented a solution that combined their all-in-one PowerTitan 2.0 system with a dedicated project team and proactive risk management. The team used closed-loop management and simulation testing to accelerate commissioning. As a result, the project achieved commercial operation just two weeks after grid connection, which Sungrow states is about 72% faster than the industry average, setting a new benchmark for BESS delivery speed in Europe.


View this case study…