Stratasys
450 Case Studies
A Stratasys Case Study
Volvo Trucks was struggling with long lead times and high costs for durable metal tooling used in engine assembly—machined tools typically took about 36 days to design and manufacture. To speed up production and increase flexibility, Volvo Trucks partnered with Stratasys and adopted a Fortus 3D Production System to print production-grade ABSplus thermoplastic tools.
Using Stratasys’ Fortus system, Volvo Trucks reduced turnaround for many clamps, jigs and fixtures from 36 days to about 2 days (a 94% time reduction), printed more than 30 production tools within three months, and lowered all-in customization cost to as little as 1 euro per cubic centimeter—roughly 1% of the cost of machined metal—while achieving 100% fit-for-purpose performance and greater responsiveness to design changes.
Pierre Jenny
Manufacturing Director