The customer, a food manufacturer, was working with electrical contractor New Era Electric to add battery storage to its solar projects in California. They needed a partner to help minimize the complexities of this process and accelerate their time to value. They partnered with vendor Stem for its energy storage solutions and expertise.
Stem implemented its Athena smart energy software and provided the battery equipment to create a 250 kW / 496 kWh energy storage system. This solution optimized the facility's utility bills, reduced expensive demand charges, and protected the value of its solar investment. Stem's expertise helped the customer achieve greater project ROI and enhanced savings.
Food Manufacturer