Case Study: a Fortune 500 building materials manufacturer cuts electricity demand and saves $1.6M CAD with Stem battery storage

A Stem Case Study

Preview of the a Fortune 500 building materials manufacturer Case Study

Fortune 500 Manufacturer

A Fortune 500 building materials manufacturer in Ontario was facing ever-rising energy costs, with two-thirds of its facility's electricity bill coming from Global Adjustment (GA) charges. The customer's challenge was manually curtailing its significant electric load in response to unreliable peak predictions, which was a cumbersome process that resulted in significant opportunity costs. The company contacted Stem to explore installing a battery energy storage system to solve this operational and financial challenge.

Stem implemented a 5.3MW / 8.5MWh battery energy storage system optimized by its Athena predictive analytics platform. The solution combined the battery system with the client's own curtailment efforts to drastically reduce electricity demand during critical peak hours. As a result, Stem helped the customer achieve annual savings of $1.6 million CAD by reducing the facility's demand by approximately 90 percent during Ontario's peak events.


View this case study…

Stem