Spotless Group
90 Case Studies
A Spotless Group Case Study
Cabrini Hospital in Malvern, Victoria, needed to relocate major engineering services plant and equipment within its live acute-care facility without disrupting hospital operations or patient care. Spotless Group, through its Nuvo brand, was engaged as the main electrical contractor and provided air-conditioning, mechanical, and electrical services for the project.
Spotless Group managed the installation and commissioning of new chillers, boilers, and other critical systems, then carefully transferred the hospital’s HVAC, mechanical, generator, electrical, fire sprinkler, and building management and controls systems. Through detailed sequencing and planning, Spotless Group ensured the work was completed with no disruption to the operational plantroom, helping Cabrini maintain continuous service delivery across the hospital.