TACSA saves €110,000 with Energy Management Strategy

TACSA, a metal-parts coating manufacturer with two plants in Barcelona, was facing rising production costs and lacked a holistic energy management plan. With energy accounting for 11% of its total expenses, TACSA turned to Spacewell Energy’s DEXMA Platform to better understand consumption and reduce costs.

Spacewell Energy helped TACSA install and analyze 18 meters across electricity and gas, create an energy team, and implement ongoing monitoring, alerts, and customized reporting. The result was €110,700 in consolidated savings, a 42% reduction in annual plant stoppages, and improved energy ratios, including a 19% drop in electricity use per production unit and a 27% drop in gas use.