Optimized Drilling System Delivers ERIELL Group's Subhorizontal Well 13 Days Ahead of Plan

SLB worked with ERIELL Group on the Urengoyskoye 4 U0406 subhorizontal development well in Russia, where the team needed to drill a 152.4-mm drain section through overpressured formations while collecting MLWD data for formation evaluation. The main challenge was maintaining wellbore stability in the narrow mud-weight window of the Achimov formation while reaching more than 80° inclination at TD.

SLB assembled a multidisciplinary team and designed a tailored drilling system using real-time drilling geomechanics, MEGADRIL oil-base drilling fluid, a PowerDrive X6 rotary steerable system, and integrated logging tools including ShortPulse, PeriScope, adnVISION, and SonicScope. The solution increased on-bottom ROP by 30% and allowed the section to be drilled and the liner run to TD 13 days ahead of plan, with no kicks or losses.


Open case study document...

SLB

768 Case Studies