Case Study: Noble Energy saves 16 hours in deepwater drilling with SLB's dual-reamer integrated drilling system

A SLB Case Study

Preview of the Noble Energy Case Study

Integrated Drilling System Saves Trip for Noble Energy in Deepwater Gulf of Mexico

SLB worked with Noble Energy on a deepwater Gulf of Mexico drilling challenge: minimizing the time needed to enlarge a rathole in a 12¼-in by 14½-in hole section without adding an extra cleanout trip. The operation required a drilling BHA that could handle hole enlargement efficiently while preserving measurement and directional performance in a complex deepwater well.

SLB designed an integrated dual-reamer drilling system using a 12¼-in MDi716 PDC bit, PowerDrive X6 rotary steerable system, Rhino XC on-demand reamer, and Rhino XS hydraulically expandable reamer, along with SLB LWD tools. The system drilled the 1,221-ft section at an average 84.5 ft/h, enlarged 178 ft of rathole from 12¼ in to 14½ in in 3.5 hours, and avoided a dedicated cleanout run, saving Noble Energy an estimated 16 hours of rig time.


Open case study document...

SLB

768 Case Studies