Case Study: a large onshore oil field operating company saves 2.5 days and USD 148,000 with SLB's integrated drilling solution

A SLB Case Study

Preview of the Large Onshore Oil Field Operating Company Case Study

Integrated Drilling Approach Achieves Single-Run Lateral to Save 2.5 Days and USD 148,000 off AFE

SLB worked with a large onshore oil field operating company in the Middle East that wanted to drill a lateral section in one run while maintaining effective hole cleaning and minimizing connection time. The company also needed to reduce flat time caused by stuck-pipe risk, bottom-up circulation, and wiper trips, while improving rate of penetration and footage drilled.

SLB recommended an integrated drilling approach using CLEAR hole cleaning and wellbore risk reduction service, PowerDrive Orbit rotary steerable system, ShortPulse integrated MWD platform, and on-rig mud supervision from M-I SWACO. The solution helped the operator achieve the lateral in a single run, reduce cumulative pill volume by 51%, avoid a wiper trip and save up to 21.5 hours, increase ROP to 91.3 ft/h from 72.3 ft/h, raise footage to 1,978 ft/d from 1,409 ft/d, cut connection time by 60%, and save 2.5 days and USD 148,000, or 32%, off AFE.


Open case study document...

SLB

768 Case Studies