SLB worked with PetroChina Company Ltd.’s Xinjiang Oilfield to improve recovery from the Huoshaoshan oil field in the Junggar Basin, where a mature waterflood had become highly irregular across a large, faulted, multilayer reservoir with complex remaining-oil distribution. The field’s traditional manual injection-allocation process was slow, taking more than a month to update all injectors, and earlier attempts to reduce water cut without hurting oil output had been inconsistent or too costly.
SLB implemented an automated workflow using the Petrel E&P software platform and ECLIPSE FrontSim streamline simulation with pattern flood management to optimize water injection allocations for individual wells. The solution increased oil production in more than 60% of the producer pilot wells, reduced water cut, lowered injection in over 50% of injectors, cut water handling costs, and reduced the time needed to determine optimal injection factors from more than a month to less than a week.