SLB worked with a large fracturing operation company in the Duvernay Shale play in Alberta, Canada, where the customer needed to reduce hydraulic fracturing costs by 30% while also lowering HSE risk. The company was dealing with a slow, expensive conventional setup with extensive flowlines and many threaded connections that created safety concerns.
SLB implemented the CAMShale fracturing fluid delivery and flowback service, including Monoline flanged-connection fracturing fluid delivery technology, the F-T90 horizontal frac tree, and a modular lightweight frac manifold. The solution reduced fracturing costs by more than 30%, cut installation time by up to 60%, eliminated 75% of connections, and helped achieve 99% uptime across 925 stages, while also improving wellsite safety.