A SLB Case Study
Casper Equipment Installation Company worked with SLB to reduce nonproductive time during rig-up of managed pressure drilling (MPD) equipment in Casper, Wyoming. The customer needed a fast, nonintrusive installation that could be completed with surface pipe work in less than 2 hours.
SLB used the @balance Xpress mobile MPD services platform with a hydraulically deployed SUPER MUD-GAS SEPARATOR to deliver a preinstalled, integrated equipment package to the wellsite. The system eliminated the need for a heavy-lift crane and welding, cut total installation time from 16 hours 20 minutes to 6 hours 40 minutes, and helped the operator skid equipment between wells with substantial time and cost savings.
Casper Equipment Installation Company