Case Study: Octavius Infrastructure saves 6 months on geotechnical scheme planning with Sensat

A Sensat Case Study

Preview of the Octavius Infrastructure Case Study

Octavius Infrastructure cuts planning time by 6 months with Sensat

Octavius Infrastructure faced a challenge when an embankment slippage threatened a major UK motorway. They needed to swiftly complete unfinished geotechnical designs and begin work before the bird nesting season to avoid months of delays. The company turned to Sensat's visualization platform to help accelerate this planning process.

Using Sensat, Octavius teams were able to accurately measure earthworks and visualize information in the context of the real world directly from their desktops. The solution from Sensat had a significant measurable impact, halving the time required for planning and client approval. A process that typically took three months was completed in just six weeks, saving an estimated six months on the overall scheme planning.


View this case study…