Iv-Infra b.v. was engaged to provide a robust tunnel condition monitoring programme for the Botlek railway tunnel in the Netherlands, where designers were concerned about ground movement. The challenge was to install an easy-to-install, accurate, and reliable monitoring system in the 1.8 km tunnel which had no cellular or internet access. Iv-Infra contacted Senceive to find a solution.
Senceive provided its FlatMesh triaxial tilt sensors, which were installed throughout the tunnel. To overcome the connectivity issue, Senceive monitoring hubs were used to relay data via a cable to a telemetry hub outside. The solution reduced manpower requirements, accelerated the programme, saved money, and eliminated the need for further maintenance. The extremely reliable Senceive system allows for remote adjustments and is planned to operate for 25 years.