RoviSys
37 Case Studies
A RoviSys Case Study
Bradley International Airport faced the challenge of modernizing its power generation to reduce emissions and improve efficiency, requiring a control system update for new Waukesha generators without disrupting daily airport operations. RoviSys was engaged to navigate this complex project, which involved outdated GE PLC code, aging documentation, and coordination with multiple stakeholders including Ameresco.
RoviSys successfully deciphered and updated the legacy GE 90-30 PLC application to integrate the new generators, ensuring a seamless transition. The result was an on-time, on-budget project that met the airport's new power requirements, allowing operations to continue smoothly and setting the stage for future upgrades. The updated system enables Bradley International Airport to operate more cleanly and efficiently.