SMP Alliance, a collaborative enterprise working on the UK's National Emergency Area Retrofit Programme, faced the challenge of coordinating a complex, multi-site project to improve road safety. With work happening simultaneously across numerous locations and involving many partners, they needed to overcome potential miscommunication and siloed information to deliver 138 emergency areas on time and within budget. They used Revizto to centralize project data and facilitate collaboration.
Revizto provided a single collaborative platform that enabled real-time sharing of 3D model-based information across all teams and partners. This streamlined communication, accelerated decision-making, and allowed for precise verification of as-built models. The solution was instrumental in helping SMP Alliance successfully deliver the ambitious programme on time and within its £362 million funding, earning them a Digital Collaboration award.