Engie gains 4 weeks on Vilvoorde BESS schedule with Procore

ENGIE, a global leader in the energy transition, faced the challenge of managing complex renewable energy projects like the Vilvoorde BESS, which required robust coordination across multiple teams and locations to integrate large-scale battery storage solutions and enhance grid stability. To boost efficiency, standardize processes, and ensure safety, ENGIE partnered with Procore.

By implementing Procore's platform to centralize data and streamline communication, ENGIE achieved significant results. These included managing over 100 projects simultaneously, achieving 600 days without lost-time injuries on the Vilvoorde project, and accelerating their schedule by four weeks. Procore enabled ENGIE to operationalize and standardize its project management globally, leading to transformative improvements in collaboration and efficiency.


View this case study…