Case Study: a large steel product manufacturer eliminates roller synchronization issues with Premier Automation

A Premier Automation Case Study

Preview of the Large steel product manufacturer Case Study

Steel Roller Speed Synchronization

A large steel product manufacturer faced a challenge where the speed of its hot steel tubes did not match the rollers catching them, causing product scrapes and frequent equipment damage. Premier Automation was engaged to develop a solution using the customer's existing Siemens PLC and drives.

Premier Automation implemented a novel solution by monitoring electrical current spikes to calculate the steel's speed, as traditional sensors were ineffective. This allowed them to reprogram the PLC and drives for synchronized speed. The results sharply diminished equipment and product damage, saving the customer thousands of dollars in repair costs per week. Premier Automation's work also eliminated quality deficiencies and reduced downtime.


View this case study…

Premier Automation

41 Case Studies