Premier Automation helped a specialty metals supplier that was struggling with outdated MG sets in its cold mill. The obsolete equipment caused frequent downtime, requiring maintenance interventions several times per shift and resulting in high costs for repairs and lost productivity.
Premier Automation solved this by replacing the MG sets with modern static DC drives and a new PLC. This upgrade provided superior control and faster strip break detection. The results included the virtual elimination of maintenance downtime, a sharp decrease in wasted materials, and an overall increase in production efficiency for the customer.