Urban Utilities engaged Pensar to address the challenge of removing the overflow risk from an existing pump station system. The project required constructing a new gravity main while the existing system had to remain fully live throughout the works, posing a significant operational challenge. Additional complexities included protecting an adjacent creek from discharge, working within a constrained site with deep excavations, and managing traffic along a major road.
Pensar implemented the solution by installing 250 meters of new gravity sewer and using tunnel boring to save native trees, including a large fig. A large temporary caisson was constructed to enable the safe installation of a new maintenance hole. Pensar successfully completed the project ahead of schedule and on budget with no lost time injuries, all while maintaining bi-directional traffic flow and keeping the system live.