Hunter Water Corporation faced the challenge of upgrading the Extended Aeration Tanks at its Toronto wastewater treatment works to improve air diffusion. The project required navigating a brownfield environment to install new diffusers and undertake significant concrete repairs while maintaining full plant operations. Pensar was engaged to provide a solution for this critical infrastructure upgrade.
Pensar successfully designed and constructed the upgrade, which included installing new diffuser systems and a specialized lifting frame. The team expertly managed the decanting and hydromining of sludge from the tanks, a process that provided a large cost benefit for Hunter Water. Through ongoing collaboration, Pensar delivered a successful outcome for all project phases, ensuring the new systems were commissioned while keeping the existing services fully operational.